Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil Construction Work For Proposed Manufacturing Plant | Project Engineering Group | Glass Process Unit | 7680 Sqmt | INR 13.01 Crores | 8 Months | Just Commenced |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Poshak Stones Pvt.Ltd.-Kalidugri,Kishangarh | URBANSCAPE ARCHITECTS | Stone Process Unit | 15000 Sqmt | INR 17.70 Crores | 6 Months | Just Commenced |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil works at Plot No. 304, Dhanora - Nandesari Road, Near ECPL, Village - Dhanora - 391346 | Shah and Talati Engineering and Architecture | Manufacturing - Furniture Fittings | 21560 Sqmt | INR 26.56 Crores | 7 Months | Just Commenced |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil works for Factory building and associated work, plot no. 741+742/1+748+749 Halol-2, Madhvas Industrial Estate Dis. Vadodara | Shah and Talati Engineering and Architecture | Engineering | 40200 Sqmt | INR 35.35 Crores | 9 Months | As Per Schedule |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Proposed Factory on Plot No.101, GIDC Palej, Dist - Bharuch | Shah and Talati Engineering and Architecture | Maunfacturing - Ropes | 15000 Sqmt | INR 14.47 Crores | 8 Months | As Per Schedule |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil work (internal & External) and Plumbing work at Halol | Ambekar Associates | Manufacturing - Glass | 21,160 Sqmt | INR 17.90 Crores | 8 mounths | 100% |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Infrastructure Development Work at RS No.12/1-12/2 Manalage, Near Karjan, vadodara | Comten Engineers | Manufacturing - Bearing | 25000 Sqmt | INR 13.33 Crores | 9 mounths | 100% |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil, Structural & Infrastructural works for Main plant (KB1) at Sanand, Ahmedabad | VMS Engineering & Design Services (P) Ltd. | FMCG | 20200 Sqmt | INR 17.29 Crore | 11 mounths | 100% |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil work for Tankfarm, Central Control Room, Roads and Drains | Cushman and Wakefield | Chemicals and Pharmaceuticals | 15,000 Sqmt | INR 15.97 Crores | 13 mounths | 100% |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil Work for Production Building and Associated Work at Halol , Line 9 & 10. | Shah and Talati Engineering and Architecture | Renewable Energy | 21,160 Sqmt | INR 35.51 Crores | 8 mounths | 100% |
---|
Name | Consultant | Industry Segment | Area | Project Cost | Duration | Present Status | Civil Work for Production Building and Associated Work (Part-1) and Civil Work for Site Development and Infrastructure Work (Part-2) at Halol , Line 7 & 8. | Knight Frank (India) Pvt. Ltd. | Renewable Energy | 1,37,500 Sqmt | INR 63.13 Crores | 6 mounths | 100% |
---|